The combined-cycle power unit will be equipped with two gas turbines, two heat recovery steam generators (HRSG), and one extraction back-pressure steam turbine. Each gas turbine, combined with a generator, will have a nominal output of 50.5MW. The HRSGs will generate super.
The combined-cycle unit will include a main operation building, a coolingsystem with auxiliary equipment, and a central control room and electric power facility. The main operation.
Electricity generated from the new unit will be transported to the electric transmission network via the existing EL-TO 110kV switchgear. Process.
In July 2018, HEP awarded the engineering, procurement and construction contract and long-term service agreement to FATA, an Italy-based company and a member of the Danieli Group. EL-TO Zagreb power plant unit A background.
European Bank for Reconstruction and Development (EBRD) and a syndicate of commercial banks are providing a €87m ($100m) loan facility.
At SolarFlex Solutions, we specialize in comprehensive energy storage products and solar solutions including energy storage products, foldable solar containers, industrial and commercial energy storage systems, home energy storage systems, communication products, and data center solutions. Our innovative products are designed to meet the evolving demands of the global energy storage, solar power, and critical infrastructure markets.
About Zagreb coal-to-electricity energy storage products video introduction
Our energy storage and solar solutions support a diverse range of industrial, commercial, residential, telecommunications, and data center applications. We provide advanced energy storage technology that delivers reliable power for manufacturing facilities, business operations, residential homes, telecom networks, data centers, emergency backup systems, and grid support services. Our systems are engineered for optimal performance in various environmental conditions.
When you partner with SolarFlex Solutions, you gain access to our extensive portfolio of energy storage and solar products including complete energy storage products, foldable solar containers for portable power, industrial and commercial energy storage systems, home energy storage solutions, communication products for network reliability, and data center power systems. Our solutions feature advanced lithium iron phosphate (LiFePO4) batteries, smart energy management systems, advanced battery management systems, and scalable energy solutions from 5kW to 2MW capacity. Our technical team specializes in designing custom energy storage and power solutions for your specific project requirements.
4 FAQs about [Zagreb coal-to-electricity energy storage products]
How many MW will El-to Zagreb power plant produce?
The new unit at EL-TO Zagreb power plant will produce 150MW of electricity and 114MW of heat. Credit: Hrvatska elektroprivreda d.d. The Elektrana-Toplana Zagreb power plant (EL-TO Zagreb power plant) located in Trešnjevka, Zagreb, Croatia, is being modernised by replacing unit A of the plant with a new combined-cycle co-generation unit.
Where is El-to Zagreb power station?
El-To Zagreb power station is an operating power station of at least 47-megawatts (MW) in Zagreb, Croatia with multiple units, some of which are not currently operating. The map below shows the exact location of the power station. Loading map... Unit-level coordinates ( WGS 84 ): CHP is an abbreviation for Combined Heat and Power.
What is EL-TO Zagreb?
EL-TO Zagreb is a power plant primarily intended for heat generation, while electricity is also generated in the process. Unit A of EL-TO Zagreb was commissioned in 1970 and has been generating electricity with a nominal output of 11MW.
Is Hrvatska elektroprivreda undertaking a modernisation project?
Hrvatska elektroprivreda is undertaking the modernisation project at EL-TO Zagreb power plant. The new combined-cycle cogeneration unit is expected to be completed by 2021. It will produce 150MW of electricity and 114MW of heat.